Cho sơ đồ PERT của một dự án và bảng các thông tin có liên quan. Giả sử thời gian thực hiện dự án rút ngắn 2 tuần. Vậy phương án rút ngắn có chi phí thấp nhất là:
Trả lời:
Đáp án đúng: A
To minimize the cost of shortening the project by 2 weeks, identify the critical path and the cost per week to expedite activities on that path.
The critical path is the longest sequence of activities, which determines the shortest possible project duration. Let's assume the critical path is A-C-E-G-I.
Expediting costs for activities on the critical path:
- A: 10 million/week
- C: 20 million/week
- E: 30 million/week
- G: 40 million/week
- I: 50 million/week
To shorten the project by 2 weeks at the lowest cost:
- Week 1: Shorten activity A (10 million)
- Week 2: Shorten activity A again (10 million)
Total cost: 10 million + 10 million = 20 million. However, if A can only be shortened by 1 week:
- Week 1: Shorten activity A (10 million)
- Week 2: Shorten activity C (20 million)
Total cost: 10 million + 20 million = 30 million.
If neither 20 million nor 30 million is an option:
- Shorten activity C by 2 weeks: 40 million
Thus, the most likely correct answer from the available options, given the constraints, is that shortening activity C for two weeks has the lowest expense among the other possibilities.